Construction of a new MV/LV cabin to serve the furnace
Modernisation and advanced automation of the low-voltage electrical system in the Parma plant

Challenge
The original installation had significant criticalities:
- Short-circuit currents exceeding the breaking capacity of the existing circuit breakers;
- Lack of adequate protection against direct and indirect contacts, with high electrical risk;
- Very long low voltage lines with a high cross section and numerous conductors in parallel, causing voltage drops and energy losses;
- Manual management of grid/genset switching, a source of errors and untimely intervention times;
- Obsolete system that does not comply with current CEI regulations in terms of safety and functionality;
Results/benefits achieved by the customer
- Improved safety with IEC 64-8 compliant and adapted protections
- Increased reliability through redundancy in switching systems and removable components
- Optimised energy efficiency through reduced cable lengths and improved power distribution
- Industry 4.0 smart integration with MODBUS TCP network, PLC and SCADA supervision for advanced monitoring and diagnostics
- Reduced downtime thanks to accurate planning and synchronised interventions with furnace rebuilds