Righi managed each phase of the project, guaranteeing quality and operational continuity:

  • Technical-economic feasibility study, with analysis of the structures and integration possibilities;
  • Producibility study, with detailed simulations to estimate the expected energy and optimise the configuration;
  • Executive design of the plant, complete with electrical and mechanical layout, according to the CEI and technical regulations in force;
  • Work management at all site phases, coordinating activities with precision and safety;
  • Installation of the photovoltaic system on the roof;
  • Testing and commissioning of the system, with verification of functional and performance conformity;
  • Drafting of a maintenance and assistance contract, agreed with the customer to guarantee operational continuity, timely interventions and monitoring of performance over time.
984-KWP—OROGEL-

Challenge

The customer needed to reduce the energy demand from the grid and to enhance the roof area of the industrial plant by installing a high-power photovoltaic system. The aim was to achieve significant energy autonomy while maintaining high standards of safety, reliability and regulatory compliance.

Results / Benefits achieved by the customer

  • Fully operational 984 kWp photovoltaic system integrated with the plant’s electrical infrastructure;
  • Significant reduction in consumption from the grid and greater energy independence for the production site;
  • Continuous post-installation support, with scheduled service contract and long-term performance monitoring.

Estimated production of approx. 1,150,000 kWh/year with savings of approx. 700,000 kWh in the bill.